Pleasant Hill Road — The Friend Compound Field Guide
Pleasant Hill Road
Type
A New Single-Family Home and Two New ADUs with an Existing Primary Home
Regulatory Approach
SB9 with lot split
City
Sebastopol (North Bay)
Total Cost
$4.2m
# of Homes
4
Cost per home
$1.0m
Timeline
21 months
Before
After
Development Approach
This compound used the following regulatory approach to develop the homes shown.
Other potential development scenarios
✓ Qualified for an ADU
This property qualifies for a new detached ADU.
✓ Qualified for SB9 Single Family Development with Optional Lot Split
This property qualifies for SB9 development and may use a lot split for 1 new primary home and up to 2 new ADUs.
— Not Applicable: SB684 Multifamily
SB684 does not apply: not multi-family zoned.
— Not Applicable: SB1123 Small-Lot
SB1123 does not apply: property is not vacant.
Timeline
Design
2 months
Permitting
8 months
Site Work
2 months
Construction
9 months
Month 0
Month 21
Design 2 months
Permitting 8 months
Site Work 2 months
Construction 9 months
Total Duration
21 months
Total Duration:
21 months (~1.8 years)
Financials
Total Project Cost
$4,155,625
4 new units · 4,500 new sf
Acquisition
24%
Soft Costs
7%
Hard Costs
69%
Acquisition ▾ $1,004,250
Soft Costs ▾ $273,875
Hard Costs ▾ $2,877,500
Unit Economics
Original Property
- Acquisition only
Build New Homes
- Soft + hard costs
All-In Total project
# of original homes
1
# of new homes
3
Total homes
4
Per Home
$1.00M
Per Home
$1.05M
Per Home
$1.04M
# of original sq ft
5,502
# of new sq ft
4,500
Total sq ft
10,002
Per Sq Ft
$183
Per Sq Ft
$700
Per Sq Ft
$415
Total
$1.00M
Total
$3.15M
Total
$4.16M
Financing Estimate
- Acquisition Loan (80%)
$780K - Construction Loan (65%)
$2.05M - Cash at Close
$224K - Cash During Build
$1.10M - Total Cash Needed
$1.33M